Spring Street reopening set for Friday

PHOTOS
 
Click on image to view.
MORE ARTICLES
DISCUSS
Comments
 

The Allen County Board of Commissioners announced that a ribbon cutting ceremony to signal completion of the Spring Street Bridge project will be held at 4 p.m. Friday. The ceremony will take place on the east side of the bridge. The public is invited to attend.

A portion of the street has been closed since May while the Allen County Highway Department and the City of Fort Wayne rehabilitated the bridge over the Norfolk Southern Railroad; reconstructed and widened Spring Street between Sprunger and Steup avenues to add turn lanes; placed signals at the intersection of Leesburg Road and Spring; and installed sidewalks along each side of the street.

Total cost of the project is around $2.27 million, with 80 percent of the funding coming from the federal government.


Comments
 
Monday
Monday
High 83 °F
Low 69 °F
73 °F
Fog/Mist
Sponsored by Masters Heating & Cooling, Inc.
LOCAL BUSINESS SEARCH
Local Search
FeaturedMore
Things To Do

STOCK SUMMARY
Dow 17098.4518.88
Nasdaq 4580.2722.58
S&P 500 2003.37+6.63
AEP 53.70+0.38
Comcast 54.72+0.20
GE 25.98-0.03
ITT Exelis 17.19+0.02
LNC 55.04+0.38
Navistar 37.71-0.12
Raytheon 96.34+0.30
SDI 23.24+0.10
Verizon 49.82+0.41
  Stock Sponsor